Latvian fire rules require a wiring check every 10 years. What the electrician measures, what goes with the report and when to check sooner.
Sep 3, 2026 · NextTek
Short answer: point 56 of the Latvian Fire Safety Regulations requires the wiring, including earthing and lightning protection, to be checked every 10 years. More often in explosive or chemically aggressive areas. There is no exemption for a flat or a private house.
The owner is responsible for fire safety in a home. In an apartment building the manager usually checks the stairwell, risers and basement. The wiring and panel inside a flat are the flat owner's part.
Point 57 and annex 6 list what has to be checked and written into the report:
Point 58 requires connections to be checked with a thermal camera, with a separate report under annex 7. The camera sees a hot screw in the panel or a loose contact in a socket before it starts to smell.
Under annex 6 the report comes with a copy of the electrician's certificate showing their electrical safety group, the calibration or verification certificate of the meter, and a diagram with the ratings of the protective devices. If anything is missing, ask for it before you pay.
Measurements are done by a certified electrical specialist (LBN 261-15, point 55). Before you book, ask for the certificate number. You can ask any electrician for it, NextTek included.
While the walls are open, replacing wires is cheap. After plastering it is expensive. The measurement shows which circuits are still fine and which must go.
The date and content of the old report tell you more than a new panel door. If there is no report at all, plan a check in the first month.
Water in a riser or wall damages insulation in ways you cannot see from outside. The insulation test shows it.
Also when a socket gets warm, a light flickers or something smells of plastic. That does not wait for year ten. The usual causes are in the post about RCDs.
The price depends on the number of circuits, the panel and whether the diagram must be drawn from scratch. A flat with one panel is often a few hours of work. An exact figure is possible from a photo of the panel and the number of circuits.
NextTek looks at the panel, fixes hot contacts and labels the breakers so a diagram is possible at all. The measurements and the report go to an electrician entitled to sign them. That is also written on the electrician page. If you plan a smart home, start here — more in the post on what to fix first.
Sources: Fire Safety Regulations (points 56–58, annexes 6 and 7), LBN 261-15 (point 55), LVS HD 60364-6. Checked in October 2026.
Tell us what you have now. We will answer with a next step, not a catalogue.